DPW Construction Projects Status

As of August 21, 2018

Route 14

PROJECT UPDATE: August 21, 2018

The Town is pleased to have received word that the Route 14 Reconstruction Project will resume at the end of this week and beginning of next week as the parties involved have resolved their issues. Milling of the road, the raising of the structures and paving of the road will be complete by the middle of September.

September 28, 2017:

From Roundabout to Stop & Shop

Drainage repair and water main repair at culvert near Lindy's.  The remainder of concrete sidewalks will be poured during the first week of October.  Roundabout to Stop & Shop and the basecoat paving is delayed until Mass DOT descision on time frame.  

From Curve St to Route 53

Box widening will continue to Route 53. Drainage work completed. Water services on on hold till the spring of 2018. 

Route 36

Have completed the 75% design phase of engineering.  A future meeting will be scheduled with the Conservation Committee.  Followed by 100% Design of engineering.  Transporation funding for the contruction project is tentatively scheduled for 2022.

Birch Street, Spring Street and Water Street

Crack sealing has been completed.  Spring Street, Birch Street and Water Street leveling course completed.  Micro Surfacing has been completed.  Stop bars and crosswalks are scheduled for the first week of October for Birch Street, Spring Street and Water Street weather permitting.  Line Painting will be done the second week of October.

Hobomock Street

Drainage work and widen of road prep work completed and Binder process done.  Granite curbing installation will be started the first week of October. New confirguration of island at the intersection of Monroe Street and Hobomock Street is completed.  New signs installed on Friday, September 8, 2017.

Line Painting

Hand crew work (stop bars and crosswalk) is planned for the first week in October.  Line painting is scheduled for the second week in October.  Weather permitting.